Refinement of observation requiremets for GOCE, Task 1


Task 1, Results and Status.


A draft contract has been prepared by ESA/ESTEC and signed by us 1998-12-10.
For further info contact the project secretary, Henriette Hansen, , e-mail: heh@gfy.ku.dk

A home-page (you are seeing it now !) has been established for the project.

Work has started Nov. 1, 1999 on Task 2 and Dec. 10 on parts of Task 3. Signed contract received from ESA Jan. 25, 1999.

Final report to be send to Main Contractor (C.C.Tscherning) at 1999-06-01. Final Report to be presented at ESTEC 1999-06-23.

Last update 1999-06-19 by CCT , e-mail: cct@gfy.ku.dk